Switzerland, LALIVE SA updates

Construction

Contributed by LALIVE SA
Model for dealing with geotechnical uncertainty: FIDIC Emerald Book for underground works
  • Switzerland
  • 29 July 2019

The 2019 Conditions of Contract for Underground Works (Emerald Book) is a new standard form specifically for underground works that is the result of a lengthy collaboration between the International Federation of Consulting Engineers and the International Tunnelling and Underground Space Association. The Emerald Book contains several features aimed at addressing geotechnical uncertainty, including geotechnical baseline reports and mechanisms to adjust the time for completion and contract price.

Swiss innovations in construction arbitration
  • Switzerland
  • 01 April 2019

New Swiss arbitration rules that are intended specifically for construction disputes contain several notable changes that may foreshadow the evolution of international construction arbitration procedures. Some or all of these innovations, which are aimed at improving efficiency and facilitating settlements, may prove to find widespread adoption among parties negotiating international construction contracts and arbitral institutions revising their rules.

Employer termination of a construction contract
  • Switzerland
  • 05 November 2018

Terminating a construction contract is the last resort for employers frustrated by delays, defects or other problems. Three recent Supreme Court cases illustrate some of the pitfalls of termination for employers. In all three cases, the employers' attempt to terminate for cause was construed as termination for convenience, exposing the employers to significant liability towards the contractors, including for lost profits.

Contractors beware: clauses requiring employer pre-approval of additional work costs
  • Switzerland
  • 10 September 2018

Clauses that require a contractor to obtain the employer's pre-approval of the cost of any additional works are increasingly common in lump-sum construction contracts. According to a recent Federal Supreme Court decision, these pre-approval clauses will be applied strictly, subject to certain exceptions. In its decision, the court enforced such a clause to deny a contractor's claim to recover the cost of additional works performed by a subcontractor.

Contractors' obligation of diligence and duty to inform persist even after termination
  • Switzerland
  • 02 July 2018

A recent decision by the Swiss Federal Supreme Court ruled that a contractor's duty of loyalty continues even after termination by the employer. When the contractor stops its works for any reason, it has the duty to take all necessary measures to prevent any harm to the employer and must provide to the employer all relevant information about the works.